Quarterly report (Form 10-Q)
CenterPoint Energy 10-Q for Quarter ended Jun 30, 2026
Filing excerpt
The PUCT has begun the process of implementing Texas Senate Bill 6 through various rulemaking processes, focused on establishing financial, operational, and interconnection requirements for large-load customers to ensure grid reliability and prevent stranded infrastructure costs. On June 18, 2026, the PUCT approved ERCOT’s Batch Zero process for large-user connection requests with the stated goal of ensuring large electricity users like data centers only connect in quantities and locations the Texas grid can reliably support.