What Dominion Energy's FY2025 10-K says: 12 signals
Dominion Energy filed its latest 10-K with the SEC on Feb 23, 2026. It discusses capacity constraint, capex increase and customer concentration.
Public (D)Oil and Gas10,000+ employeesdominionenergy.comLinkedIn
- Filed
- Feb 23, 2026
- Period
- FY2025
- Fiscal year end
- 12/31
- Filings
- 1
10-K · latest 5
What Dominion Energy's 10-K filings say
- SEC EDGAR
10-K · FY2025
Filed · Fiscal year ends 12/31 · 12 signals
CVOW offshore wind project hit with $258M in unrecoverable costs in 2025
The company's flagship Coastal Virginia Offshore Wind (CVOW) project cost estimate increased to $11.5B, resulting in a $258M charge for unrecoverable costs due to work suspensions, tariffs, and network upgrade costs.
$258M
Charge for unrecoverable costs on the CVOW Commercial Project in 2025.
offshore windPJMStonepeak
Dominion Energy launches $65B capital expenditure plan for 2026-2030
The company has a $65 billion capital plan through 2030 focused on grid transformation, renewable generation, and resiliency to meet projected demand growth.
$65B
Capital expenditure plan for 2026 through 2030.
offshore windsolarnuclear
Data centers now 28% of Virginia Power's electricity sales, creating significant demand challenges
A surge in demand from data centers, which now represent 28% of electricity sales, is creating a unique challenge and requires significant investment in new generation and transmission.
28%
Percentage of Virginia Power's electricity sales from data centers in 2025.
PJM
Completed sale of gas operations to Enbridge for over $9.3B, refocusing on electric utilities
Dominion has divested its gas distribution operations in a series of transactions, signaling a major strategic shift.
$9.3B
Total cash consideration from sales of gas operations to Enbridge
Enbridge
CVOW project hit by recurring cost overruns, including a $103M charge in late 2024
Prior to a larger 2025 charge, the company recorded a $103 million charge in Q4 2024 for its share of unrecoverable costs on the CVOW project.
$103M
Charge for unrecoverable costs on the CVOW Commercial Project in Q4 2024.
offshore windPJM
Showing 5 of 12 filing signals. The Signal API returns all of them.
Get them with one API callSignal API · MCP
Track Dominion Energy with the Signal API
One POST /v1/companies/enrich call with dominionenergy.com returns Dominion Energy 10-K signals (sec-10k), each with its source. Or ask Claude through MCP.
2 credits per signal returned; zero-result calls are free. Endpoint reference
curl -X POST https://signals.autobound.ai/v1/companies/enrich \
-H "X-API-KEY: $AUTOBOUND_API_KEY" \
-H "Content-Type: application/json" \
-d '{"domain":"dominionenergy.com","signal_types":["sec-10k"],"limit":20}'Same industry
10-K at related companies
Questions about Dominion Energy 10-K
When did Dominion Energy file its latest 10-K?
What does Dominion Energy's latest 10-K say about supply chain disruption?
Where can I find Dominion Energy's annual report?
Source. Annual reports (Form 10-K) filed with the SEC. Every card links to the filing on EDGAR.
Method. Insights are extracted from the filing text and grouped by category. Numbers are quoted from the filing.